Project Schedule Performance Index (SPI)

Earned value relative to planned value for project timing

FORMULA

SPI = Earned Value (EV) / Planned Value (PV)


Alternate Calculations

Schedule VarianceEV - PV (in dollars)

What is Project Schedule Performance Index?

Schedule Performance Index measures project progress efficiency by comparing Earned Value (work completed) to Planned Value (scheduled work). SPI = EV / PV. Critical for construction project management. SPI > 1.0 indicates ahead of schedule; SPI < 1.0 indicates behind schedule. Used to forecast project completion and identify schedule risk.

Chart

Edit the data below to update the chart. Download as PNG or SVG — free, no sign-up required.

CSV or tab-separated format · edit to update chart live · 4 rows

Sample Data

weekpvevspistatus
1100,00095,0000.95At Risk
2200,000205,0001.025On Track
3300,000315,0001.05Ahead
4400,000420,0001.05Ahead